Whalen Company 2 Pipe Fan Cycle Fan Coil Order of Operations
The thermostat sends power to the aquastat.
The aquastat, if in heat mode and there’s hot water in the pipes, will allow the fan signal to energize a fan cycle relay, which turns the fan on.
If in cooling mode, while there’s hot water in the risers, it will not allow the fan cycle relay to engage, so the fan won’t work.
Report
There was a problem reporting this post.
Block Member?
Please confirm you want to block this member.
You will no longer be able to:
See blocked member's posts
Mention this member in posts
Invite this member to groups
Message this member
Add this member as a connection
Please note:
This action will also remove this member from your connections and send a report to the site admin.
Please allow a few minutes for this process to complete.